Location: Sudair, Riyadh Province
Technology Type: Solar PV
Production Capacity: 1,500 MW power
Development Model: Independent Power Project
Project Cost (SAR bn): 3.4
Offtake Contract: SPPC (Power)
Commercial Operational Date: Nov 2024
Solar PV project in Sudair, Riyadh Province, developed under the IPP model with a 35-year contract. The project produces 1,500 MW of power. SPPC is the offtaker. Financial close was achieved in April 2021 and operations began in October 2024.